Do subcontractors need their own RAMS?
Short answer: in practice, yes. The law doesn't use the word "RAMS". But every subcontractor, whether a company or a self-employed tradesperson, must assess the risks of its own work, and on a construction project every contractor must plan, manage and monitor the work it does. A risk assessment and method statement written for the job is how you show the principal contractor you have done that.
What the law actually requires
- A risk assessment. Regulation 3 of the Management of Health and Safety at Work Regulations 1999 says every employer must make a suitable and sufficient assessment of the risks to its employees and to anyone else affected by its work. The same duty applies to a self-employed person whose work is of a prescribed description.
- Self-employed people on site are covered. The prescribed list includes any work carried out on a construction site, and any work that gives rise to a duty under CDM 2015. HSE says this applies on commercial sites and in domestic premises.
- Writing it down. An employer with five or more employees must record the significant findings of the assessment (regulation 3(6)).
- Planning your own work. Under regulation 15 of the Construction (Design and Management) Regulations 2015, a contractor must plan, manage and monitor the construction work it and its workers carry out, so that so far as is reasonably practicable it's done without risks to health and safety.
- Following the principal contractor. Where there's more than one contractor, each must comply with the principal contractor's directions and with the parts of the construction phase plan that relate to its work (regulation 15(3)).
Notice what isn't there: neither CDM 2015 nor the 1999 Regulations use the words "method statement" or "RAMS". The method statement is the industry's way of setting out how the job will be done safely, step by step, using the controls the risk assessment identified.
Why the principal contractor asks for yours
CDM 2015 makes the principal contractor plan, manage, monitor and coordinate the whole construction phase, organise cooperation between contractors and make sure a suitable site induction is given (regulation 13). It can only do that if it knows how each trade intends to do its part. That's why most principal contractors won't let a subcontractor start until they've seen and accepted its RAMS.
HSE's guidance on CDM 2015 (L153) says the principal contractor's construction phase plan should not be cluttered with generic risk assessments or detailed safety method statements. Those sit with the contractors who do the work, which is another reason the principal contractor expects each subcontractor to bring its own.
Can you rely on someone else's RAMS?
Not instead of your own. The duty to assess the risks of your work to your own people and to others belongs to you, as the employer or self-employed person. You can, and should, read the principal contractor's site rules and construction phase plan and make your RAMS fit them. But a main contractor's document covers their work and their arrangements, not your sequence, your plant and your materials.
The same goes for a RAMS copied from your last job. A risk assessment must be suitable and sufficient for the risks it covers. If it describes a different site, different access or different plant, it isn't.
What a subcontractor's RAMS should cover
- The job, the site and who is doing the work, with their training or cards where the principal contractor asks for them.
- The hazards of your tasks on this site, who could be harmed, and the controls.
- A step-by-step sequence of work, from arriving on site to handover.
- Access, working at height, plant and equipment for this job.
- Hazardous substances you'll use, with COSHH assessments where needed.
- How your work interacts with other trades and the public, and how you'll follow the site rules.
- Emergency and rescue arrangements for this site.
- A sign-off by your competent person, and a briefing record for the workers who'll use it.
Before you send it
- Ask the principal contractor for their RAMS requirements or check sheet, and follow its layout.
- Read their site rules and the parts of the construction phase plan that affect your work.
- Check every page describes this job, not the last one.
- Have your own competent person, who knows the site, check and sign it.
- Brief your workers on it before they start, and update it if the job changes.
Frequently asked questions
Is RAMS a legal requirement?
The term RAMS does not appear in the law, and neither CDM 2015 nor the Management of Health and Safety at Work Regulations 1999 uses the words method statement. What the law does require is a suitable and sufficient risk assessment, and on a construction project each contractor must plan, manage and monitor its own work. A RAMS is the usual way of showing a principal contractor that you have done both.
Do self-employed subcontractors need a risk assessment?
Yes, for construction work. The risk assessment duty applies to self-employed people whose work is of a prescribed description, and the prescribed list includes any work carried out on a construction site and work that gives rise to a duty under CDM 2015. HSE says this applies on commercial sites and in domestic premises.
Do I have to write my risk assessment down?
The law requires an employer with five or more employees to record the significant findings of the assessment. In practice, a principal contractor will almost always want to see it in writing before you start, whatever your size.
Can I just use the main contractor's RAMS?
Not as a substitute for your own. The duty to assess the risks of your work to your own workers and others sits with you as the employer or self-employed person. You must also follow the parts of the principal contractor's construction phase plan and any directions that apply to your work, so your RAMS should fit with theirs.
Does the principal contractor have to accept my RAMS?
The principal contractor must plan, manage, monitor and coordinate the construction phase, and contractors must comply with its directions. If your RAMS does not match the job or their site rules, they can ask you to change it before you start.
Does a generic RAMS count?
A risk assessment has to be suitable and sufficient for the risks it covers. A generic document copied from another job often misses the site's actual access, sequence, plant and neighbours, which is a common reason RAMS are sent back. HSE's CDM guidance also warns against generic risk assessments cluttering the construction phase plan.
Sources
All last checked 26 October 2026. Laws and guidance change, so check the source before relying on a date or figure.
- Management of Health and Safety at Work Regulations 1999, regulation 3 (risk assessment)
- Construction (Design and Management) Regulations 2015 (regulations 13 and 15)
- The Health and Safety at Work etc. Act 1974 (General Duties of Self-Employed Persons) (Prescribed Undertakings) Regulations 2015, Schedule, paragraph 3 (construction)
- HSE: High-risk work activities that apply to the self-employed
- HSE: CDM 2015, contractors
- HSE: CDM 2015, principal contractors
- HSE L153: Managing health and safety in construction, Appendix 3 (the construction phase plan)