Remit Docs

Section 20 consultation: the process, stages and timeline

If you're a director of an RTM company or RMC, or you run a small share-of-freehold block yourself, section 20 consultation is one of the few parts of leasehold law you cannot afford to get wrong. Get it wrong and each leaseholder's share of the bill can be capped unless a tribunal agrees to excuse the failure. This guide sets out what has to happen, in order, with a worked timeline and the points where consultations most often fail.

This is written for England. The Service Charges (Consultation Requirements) (England) Regulations 2003 (SI 2003/1987) apply in relation to England only, and Wales has its own 2004 regulations, so don't rely on this for a Welsh block. It covers the usual route for qualifying works where no public notice is needed (Schedule 4, Part 2 of the Regulations). Works or agreements that need a public notice follow a different route and are not covered here.

Do you need to consult? The £250 and £100 triggers

Consultation under section 20 of the Landlord and Tenant Act 1985 is triggered by:

Work out the trigger before you do anything else, using each leaseholder's actual contribution under their lease, not an average. A leaseholder's "relevant contribution" is the amount the lease requires them to pay towards the cost.

Don't split one connected project into smaller jobs to keep each below £250 per leaseholder. If you are unsure whether works are really one project, take advice before deciding not to consult.

The section 20 process at a glance (flowchart)

For qualifying works with no public notice, read this top to bottom. Each arrow is a step you must complete before the next.

  1. Check the trigger. Is any leaseholder's share above £250? If not, section 20 does not apply to these works.
    ↓
  2. Notice of intention. In writing, to every leaseholder who will contribute and any recognised tenants' association. This starts the first 30-day period.
    ↓
  3. Within the 30 days: leaseholders send written observations and may nominate someone to provide an estimate.
    ↓
  4. Your move: have regard to the observations, try to get an estimate from any nominee in the cases the Regulations set out, and obtain estimates (at least one from someone wholly unconnected with you).
    ↓
  5. Statement of estimates and notice. Show the cost in at least two estimates, summarise the first-stage observations and your response, and invite observations on the estimates. This starts the second 30-day period.
    ↓
  6. Within the second 30 days: leaseholders send observations on the estimates.
    ↓
  7. Your move: have regard to those observations, then choose your contractor and enter into the contract.
    ↓
  8. Notice of reasons. Within 21 days of entering into the contract, give each leaseholder your reasons for the award (or say where they can be inspected). Not needed if the contractor was a nominated person or gave the lowest estimate.

How long is a section 20 notice period?

Each consultation period is 30 days beginning with the date of the notice. For qualifying works there are two: one after the notice of intention and one after the statement of estimates.

The Regulations define the "relevant period", in relation to a notice, as "the period of 30 days beginning with the date of the notice" (regulation 2(1)). So day one is the date on the notice: a notice dated 4 January has its 30th day on 2 February. The notice must itself state the date on which the period ends (Schedule 4, Part 2, paragraphs 1(2) and 4(10)).

Because the period runs from the date of the notice, date it on the day you actually send it. (This is a practical point, not a rule in the Regulations. How a notice counts as given is a matter for your lease and the general law, so check how yours must be served.)

You must also have regard to observations made within each period (Schedule 4, Part 2, paragraphs 3 and 5). It follows, on a sensible reading, that you cannot properly have regard to observations before the period has ended, so don't award the contract or start work until the second period has closed.

Section 20 timeline: a worked example with dates

This is an illustration only. The dates are invented and assume nothing goes wrong. The Regulations set the 30-day and 21-day periods; the rest is your own planning.

StepExample dateBasis
Notice of intention dated and sentMon 4 Jan 2027Day 1 of the first period
Last day for observations and nominationsTue 2 Feb 2027Day 30, counting 4 Jan as day 1
Obtain estimates3 Feb to 19 Mar 2027Assumed, about six weeks. The Regulations do not appear to set a deadline for this step, so allow what your contractors need
Statement of estimates and notice dated and sentMon 22 Mar 2027Day 1 of the second period
Last day for observations on the estimatesTue 20 Apr 2027Day 30, counting 22 Mar as day 1
Consider observations, then enter into the contractMon 3 May 2027Assumed
Notice of reasons due, if requiredBy Mon 24 May 2027Within 21 days of entering into the contract

On these dates the process takes about 17 weeks from first notice to contract, before any works begin. Build that into your programme, especially if a contractor's price is only held for a limited time.

If you would rather have every date worked out from your own start date, or backwards from a target date for works on site, the Section 20 Planner does that for qualifying works in England. It does not cover qualifying long-term agreements.

What must a section 20 notice of intention contain?

It must be in writing and given to each leaseholder and any recognised tenants' association. It must describe the works in general terms or say where and when a description can be inspected, give your reasons for considering the works necessary, invite written observations, say where to send them and the date the 30-day period ends, and invite leaseholders to nominate a person to provide an estimate.

In list form, the notice (Schedule 4, Part 2, paragraph 1) must:

If the notice gives a place and hours for inspection, they must be reasonable and the description must be available free of charge. If it cannot be copied at that time, you must give a free copy to any leaseholder who asks (paragraph 2).

Example wording: an illustration, not a template

This shows how those required points can read in plain English. It is not a legal template and not legal advice. Adapt it to your block and take advice before serving anything.

We intend to carry out [general description of the works] at [address]. We consider the works necessary because [reasons]. A description of the proposed works can be inspected free of charge at [place] between [hours]. You may send written observations to [address]. They must be delivered by [last day of the 30-day period]. You may also propose in writing, by the same date, the name of a person from whom we should try to obtain an estimate.

Common mistakes. Missing a leaseholder off the list. Describing the works so vaguely that leaseholders cannot respond. Leaving out your reasons. Stating the wrong end date for the period. One missed leaseholder can be enough to unpick the process for that flat, so get the list right at the outset.

Nominating a contractor: what you have to do

Leaseholders and any recognised tenants' association can propose a person for you to ask for an estimate. You are not required to appoint the nominee, but where a nomination is made you must try to get an estimate from them in the cases the Regulations set out (Schedule 4, Part 2, paragraph 4):

Stage two: estimates and the statement of estimates

After the first period closes you must obtain estimates and then (paragraph 4):

Common mistakes. Proceeding on one estimate. Ignoring a nomination without trying to get an estimate. Leaving out the summary of observations and your response. Signing the contract before the second period has ended.

What to do with observations you receive

You must have regard to observations made within either period. That doesn't mean adopting every suggestion, but it does mean genuinely considering them. Keep a simple written record of what was raised and how you responded, even informally at board level. It is the easiest thing to produce if anyone later challenges the process.

Stage three: notice of reasons for the award

The Regulations call this the duty on entering into a contract (paragraph 6). Within 21 days of entering into the contract you must tell each leaseholder and any recognised tenants' association, in writing, your reasons for awarding it, or say where those reasons can be inspected. If you received observations on the estimates, you must also summarise them and set out your response.

You do not need to give this notice if the contractor was a nominated person or submitted the lowest estimate.

Qualifying long-term agreements (QLTAs) in brief

A QLTA is an agreement entered into by or on behalf of the landlord or a superior landlord for a term of more than twelve months (section 20ZA(2)). Consultation applies where a leaseholder's contribution in an accounting period would be more than £100 (regulation 4). Some agreements are excluded, for example contracts of employment (regulation 3).

QLTAs follow different Schedules: Schedule 1 where no public notice is required, Schedule 2 where it is, and Schedule 3 for qualifying works carried out under a QLTA to which section 20 applies. The steps include a notice of intention and, in Schedules 1 and 2, the landlord's proposals. Because these routes are more involved, take advice before relying on this summary for a long-term contract.

Section 20B: the 18-month rule

Section 20B is a separate rule from consultation. If any of the relevant costs in a service charge were incurred more than 18 months before a demand for payment is served on the tenant, the tenant is not liable to pay that part. The exception is where, within 18 months of the costs being incurred, the tenant was notified in writing that the costs had been incurred and that they would later be required to contribute to them through a service charge (section 20B(1) and (2)). Check the current wording on legislation.gov.uk before relying on it, as amendments to this section are shown as not yet applied.

What happens if a landlord gets section 20 consultation wrong?

Unless the consultation requirements were complied with or dispensed with by the First-tier Tribunal, each leaseholder's contribution is limited to £250 for qualifying works, or £100 per accounting period for a qualifying long-term agreement. The landlord can apply to the tribunal for dispensation under section 20ZA.

Section 20ZA(1) says the tribunal "may make the determination if satisfied that it is reasonable to dispense with the requirements". Since Daejan Investments Ltd v Benson [2013] UKSC 14, the central question is whether the leaseholders were prejudiced by the failure. Dispensation is not automatic: the legal burden stays on the landlord, and the tribunal can attach conditions, including a costs condition. Our guide to section 20 dispensation explains the test, the conditions and how to apply. Leaseholders reading from the other side may find our section 20 notice guide for leaseholders useful, since it shows what they will be told and what they can do.

Can you ask for dispensation before urgent works?

Yes. In Daejan the Supreme Court said it is clear that a landlord may ask for dispensation in advance, giving works that must be done very urgently, and works found to be necessary while contractors are already on site, as the most obvious cases (para 56). Don't treat dispensation as a routine substitute for consultation. If you think you need it, apply as early as you can rather than after the event.


This is general information, not legal advice, and it covers England only. For a specific consultation, particularly anything contested or high-value, involve a solicitor, a qualified managing agent or a surveyor, or check with the First-tier Tribunal or LEASE before you serve anything.

Running a consultation? The Section 20 Planner (£99) sets out the dates and notices for each stage. Or start with the free Section 20 Free Check. See it on the shop